Here's our progress for week 1. Demo - complete. Cleanup - 95% done. Framing - Complete. Electrical - 50% done (as much as can be done before the drop ceiling goes in. Plumbing - 30% done. Shower installation - 10% done, but the hardest 10%. We're not as far along as I initially hoped because the extra framing slowed us down. But I'm still very pleased with progress thus far.
By this time next week we should be mudding drywall. One more pic for this week... We brought the old tan dump truck over to load all the bathroom debris into. Of course Nate had to drive, just like he does every other truck he sees. Tell me this doesn't look just like Grandpa Mike at that age...